Près d'un siècle d'expérience au service des ouvrages de demain

Information sheet 98

Our Constructions > Docks and Piers

 

Boom J in the Port of Cavalaire

Boom J in the Port of Cavalaire

The reconstruction of this boom lasted 14 days, from the arrival of the floating crane to the delivery of the project!

Placement of the concrete spans, hammering of the guide piles, the removal of the existing crossheads, cutting down of the piles, installation of the new boom, and all of these operations lasted barely 3 weeks.

This gives a good insight into Negri’s capabilities!

Amount: 90 k€

Project manager and contracting authority:

City of Cavalaire

Boom J in the Port of Cavalaire Boom J in the Port of Cavalaire